The manufacturer of the finished machine, or the installer of the UCC2, is responsible for ensuring that the following testing and verification, to the appropriate standards, is performed as a minimum on the complete installation.

  • Verification that the electrical equipment is in compliance with the technical documentation.
  • Continuity of the protective bonding circuit.
  • Insulation resistance tests.
  • Voltage tests.
  • Protection against residual voltages.
  • Functional tests, particularly those related to safety and safeguarding.